How Project Planning Works

Joakim Aspegren, President
Architecture Restoration Conservation (ARC)

The Lay of the Land

One piece of advice I can offer to a board: do not underestimate the importance of planning for major capital improvement projects.

Unfortunately, most co-op and condo boards are so focused on day-to-day issues that they don’t think enough about the long-term challenges that they may face. Most of these challenges can be easily anticipated, and the benefit of addressing them early can be substantial.

Typically, most boards will just need to obtain an estimate to get a sense of how much a capital improvement project will cost. I strongly recommend that those estimates be prepared soon after a project has been identified. I also recommend that those estimates be prepared by the architect or engineer who will be responsible for developing the final scope of work, as they will be most familiar with the issues at hand. It would be wise to verify a firm’s budgeting capabilities before engaging it for a capital improvement project.

Adequate planning provides the time needed to raise funds required to address major projects. Since most projects do not have to be undertaken right away, spending 1 to 3 percent of a project’s budget to develop a plan is, in my view, money very wisely spent.

Planning ensures that the projects can be adequately funded and that the money will be in place when needed; it also eliminates surprise and uncertainty. Lack of planning, on the other hand, can be financially devastating, draining reserves to the point where projects, some of which might be required by law, have to be cancelled or postponed because of a lack of funds.

Now What?

The money already spent on architectural or engineering services will go to waste if the project cannot move forward. An example of this is a client of ours for whom we prepared a Cycle 7 facade inspection report four years ago. They waited two years before bringing us back to produce the construction documents that would be used to solicit bids. When they received the bids, they didn’t have the money to do the project. The job has been on hold for over two years now.

In January of this year, Cycle 8 came up. Because none of the repairs related with the Cycle 7 had been addressed, the building was automatically classified as unsafe. The board was required to install a sidewalk shed, and they’re now spending thousands of dollars a month in sidewalk shed rental fees, in addition to all of the expenses associated with filing fees required because of their unsafe status.

If they’d had a plan in place, they could have had at least two more years to raise the funds needed to undertake the project. And they probably would have been in a much better situation than they are now. Remember: when undertaking a capital improvement project, money spent up front on developing budgets is a very wise investment.

Subscriber Login


Ask the Experts

learn more

Learn all the basics of NYC co-op and condo management, with straight talk from heavy hitters in the field of co-op or condo apartments

Professionals in some of the key fields of co-op and condo board governance and building management answer common questions in their areas of expertise

Source Guide

see the guide

Looking for a vendor?