SEEKING BOARD MEMBER FROM SMALL CONDO ASSOCIATION THAT HAS HAD SIGNIFICANT REPAIR WORK DONE!Mar 10, 2014

I'm on the board of a small (11 units) condo association, and we need substantial exterior repair work done. Unfortunately the entire board turned over six months ago, and the new board is willing but inexperienced. We solicited bids from engineers to put together a Request For Proposal from contractors, and the engineering proposals themselves have us spinning--tens of thousands just for the engineering company to oversee the work, which will be hundreds of thousands...and there are only 11 units! We are looking for other board members who have been down this path and who have learned from the experience to help us try to navigate our course. ANY suggestions or recommendations regarding hiring an engineer, contractor, permits, financing, communication with other owners, etc. etc. would be greatly appreciated! Thank you.

Join the Conversation Comments (2)
Seeking Board Member from Small Condo Association Response - CondoGuy1 Mar 12, 2014

i am the treasuer of a 30 unit condo that did a ton of work following Sandy. It is difficult as very few places give condo loans to associations and places that do like like NCB are very expensive and charge a lot of fees and payback is usually over ten years.

I would honestly start with finding a few good contractors and get some estimates even before you engage engineers.

Also are folks current in the maint and do you know if folks have equity in their units. After Sandy we now have several units no longer paying maint. The trouble with the loan. Is you could borrow with assumption 11 folks will be paying it back and find out only 7 are chipping in as maint went up.

Also is this just pointing work or is balconies and windows included? Big difference difference. Also read your offering plan very carefully and dont assume something is a building responsibility when they are not. I was suprised in my building windows and balconies and doors are owners resonsiblity. Nearly all condos that is condo associations job. .

Thank you for rating!

You have already rated this page, you can only rate it once!

Your rating has been changed, thanks for rating!

Introduce yourself to other members of Board Talk! Login below or register here.

Board Talk members who registered prior to March 9th, 2016 will need to reset their password.

Register

Forgot your password? Click here

> Join the conversation Comments (1)
repairs - Marin Mar 13, 2014

Thank you, CondoGuy1! We can just contact contractors, but I'm not sure how to get quotes from them when we don't know everything that needs to be done--we know there is repair work above street level, and roof work, but don't know the extent of it. Do you have any thoughts on how to get a quote when we aren't building-savvy and can only see the tip of the iceberg of building issues? And the issues are structural, not windows or balconies. Also, did your building in fact get a loan? We are assuming we can get one but we have yet to look into the criteria/costs involved. Please feel free to email me back at charaa@aol.com, I so appreciate the benefit of your experience--I'd be happy to speak on the phone if that's more convenient for you. Best wishes, Marin

Thank you for rating!

You have already rated this page, you can only rate it once!

Your rating has been changed, thanks for rating!

Introduce yourself to other members of Board Talk! Login below or register here.

Board Talk members who registered prior to March 9th, 2016 will need to reset their password.

Register

Forgot your password? Click here

> Join the conversation
repairs - co-op_owner Mar 12, 2014

We just did quite a bit of work for Local Law 11. Our architect recommended contractors, all of whom were well above our price range. we did our own search and ended up saving close to half. If you would like to give me your email, I would be happy to message you with the names of those contractors and what we thought of them. Our work is now down and while our experience wasn't seamless, saving $100K made the few small issues seem like nothing.

Thank you for rating!

You have already rated this page, you can only rate it once!

Your rating has been changed, thanks for rating!

Introduce yourself to other members of Board Talk! Login below or register here.

Board Talk members who registered prior to March 9th, 2016 will need to reset their password.

Register

Forgot your password? Click here

> Join the conversation Comments (1)
Saving $$ - Marin Mar 13, 2014

Thank you! My email is charaa@aol.com, and I'd be happy to hear any info about the contractors, or to speak by phone and take notes on your experience, whatever is easier and less of an imposition on you. I look forward to hearing back! Marin

Thank you for rating!

You have already rated this page, you can only rate it once!

Your rating has been changed, thanks for rating!

Introduce yourself to other members of Board Talk! Login below or register here.

Board Talk members who registered prior to March 9th, 2016 will need to reset their password.

Register

Forgot your password? Click here

> Join the conversation Comments (1)
just sent an email - co-op_owner Mar 14, 2014

hello, just sent you a message with info. if you want to chat, respond and leave me your number!

Thank you for rating!

You have already rated this page, you can only rate it once!

Your rating has been changed, thanks for rating!

Introduce yourself to other members of Board Talk! Login below or register here.

Board Talk members who registered prior to March 9th, 2016 will need to reset their password.

Register

Forgot your password? Click here

> Join the conversation Comments (2)
Local Law 11 work - dsi1 Mar 17, 2014

This is complex and involved major piece of work that has to be done correctly and certified. There is absolutely no point in going to a contractor without having a clear set of specs and plans in place. The answers you will get will be worthless, and likely cost you many times what you think it will cost.

The work involved covers: parapets, caps & copings, drainage, masonry, pre-cast sills, lintels, facade cracks, cutting & caulking, Terra-Cotta repair and sealing work. This can include, as in our building, the fact that the original mounting straps holding the T-C to the facade were pulling away from the building, necessitating an expensive and carefully engineered process and design solution for dismantling, replacing corroded straps with new SS straps, and re-installation. Then there are the fire-escapes, windows and sealants, roof inspection, elevator head/housing, gutters, pointing and ironwork.

There are architects and Engineers who both specialize in this work. They will have to do a very close inspection, photograph everything, and draw up detailed plans, devise the exact specs on how it will be dealt with, the products to be used, especially if they have to replace bricks and mortar that needs to match, and be knowledgeable in how a building constructed at the time yours was, was actually built.

There are three phases to the Architect's job: P1 - the site inspection and the specification work, the analysis and design documentation and technical drawings, bid documents and refereeing the site surveys by bidding contractors (on-site scheduled meetings) bid review, and advisement on selection and negotiations. P-2 is: the on-site inspection of the work being done by the contractor (how many visits you will require them to make for each significant type of work) and any additional on-site discoveries and solutions, or for that matter the Architect requiring them to redo work they have completed as insufficient, improperly executed, etc. not extensive enough, or the Contractor finding things and going to the Architect and saying you missed this, or we have found hidden damage you could not have foreseen etc. (they need to work well together). You need the Architect o see and approve all replacement bricks and mortar to ensure a proper match). The end of this phase is the Architect's sign-off on the Contractor's job. P-3 is: the Architect's final report and inspection notes, certification and stamps to the DOB and their inspection, with the Architect of the job.

You will probably have to put up a bridge on the street side of your building. That is expensive, so do everything you need to and do everything preventative as well. Spend the money once. P1 - a couple of years back ran us $15K, P2, $4,500, and P3 $2.5K, the bride alone was $20-25K on a 6 story street side facade (rest of building is 7 stories/30 units. facade work ran us about $135K We had to do this twice in a 5 year period because of storm damage. Without a plan in hand, the variables that Contractors will tell you are huge, when you compare bids it is startling how the prices for similar items will vary, based on their own resources and way of doing the same job. Bid five+ in the hopes that you get back 3 usable bids. Insist that everything be line itemized, and that materials and labor be broken out separately and itemized. Retain the exclusive right to amend the RFQ so you can drop/add/modify sections or elements after receiving bids to make it affordable. We dropped out almost $40K in pre-cast custom sill replacements and substituted caulking all around and of any sill cracks thereby replacing only 5 of over 140+ sills. If you do not have a qualified building management construction person to Supervise the job from your end, then you will have to do it, overseeing the Architect. Do not allow your Management company to just supply you with a contractor, DO the work, interview architects and Engineers, interview Contractors with the Selected Architect/Engineer. This is a ferociously expensive project that can quickly go out of control, AND if not done correctly, can have you doing it over in less than five years at greater expense. A good architect and a good contractor will help you, will find ways to save you money and working together do it better, safer, and a hopefully more durable job. I would say we have been lucky, but we have good Management, and we made our own luck thru diligence.

I am sure I must have left somethings out, but this is the general idea, anyway.

As to windows and doors, and who is responsible. That will be in your proprietary lease, Bylaws etc. (I am Coop oriented), regardless of how it falls out, you do not want individual owners replacing windows with whatever they want, in whatever color they want, and whatever quality they feel like, You need to set up a building wide plan for replacements, pick you price point, color and style and stick firmly to it, and asses them all accordingly. You do want to hire an Architect to consult as it can be complicated as to choice and needs.

There is no viable shortcut around using experts. Whether it be Architects and Engineers, CPA's, Certiorari work or licensed tradesmen.

It will always save you either money, grief or both. These are big ticket projects, requiring permits and DOB filings. You don't want the supplier acting as his own supervisor, really! You don't need a big fancy architect or Engineering firm. You can do with a small practice office with really smart and skilled people. IT can be a solo outfit. Just do your homework, knock on doors, if you see a job being done, ask questions, find out if everyone is happy with the execution of the job. Drive around the neighborhood, Check habitat articles for Vendors who did well, and who to avoid, there are plenty of those around!
To do it right is a lot of work, to do it wrong is even more work,
Good luck.

Thank you for rating!

You have already rated this page, you can only rate it once!

Your rating has been changed, thanks for rating!

Introduce yourself to other members of Board Talk! Login below or register here.

Board Talk members who registered prior to March 9th, 2016 will need to reset their password.

Register

Forgot your password? Click here

> Join the conversation
Local Law 11 work - dsi1 Mar 17, 2014

This is complex and involved major piece of work that has to be done correctly and certified. There is absolutely no point in going to a contractor without having a clear set of specs and plans in place. The answers you will get will be worthless, and likely cost you many times what you think it will cost.

The work involved covers: parapets, caps & copings, drainage, masonry, pre-cast sills, lintels, facade cracks, cutting & caulking, Terra-Cotta repair and sealing work. This can include, as in our building, the fact that the original mounting straps holding the T-C to the facade were pulling away from the building, necessitating an expensive and carefully engineered process and design solution for dismantling, replacing corroded straps with new SS straps, and re-installation. Then there are the fire-escapes, windows and sealants, roof inspection, elevator head/housing, gutters, pointing and ironwork.

There are architects and Engineers who both specialize in this work. They will have to do a very close inspection, photograph everything, and draw up detailed plans, devise the exact specs on how it will be dealt with, the products to be used, especially if they have to replace bricks and mortar that needs to match, and be knowledgeable in how a building constructed at the time yours was, was actually built.

There are three phases to the Architect's job: P1 - the site inspection and the specification work, the analysis and design documentation and technical drawings, bid documents and refereeing the site surveys by bidding contractors (on-site scheduled meetings) bid review, and advisement on selection and negotiations. P-2 is: the on-site inspection of the work being done by the contractor (how many visits you will require them to make for each significant type of work) and any additional on-site discoveries and solutions, or for that matter the Architect requiring them to redo work they have completed as insufficient, improperly executed, etc. not extensive enough, or the Contractor finding things and going to the Architect and saying you missed this, or we have found hidden damage you could not have foreseen etc. (they need to work well together). You need the Architect o see and approve all replacement bricks and mortar to ensure a proper match). The end of this phase is the Architect's sign-off on the Contractor's job. P-3 is: the Architect's final report and inspection notes, certification and stamps to the DOB and their inspection, with the Architect of the job.

You will probably have to put up a bridge on the street side of your building. That is expensive, so do everything you need to and do everything preventative as well. Spend the money once. P1 - a couple of years back ran us $15K, P2, $4,500, and P3 $2.5K, the bride alone was $20-25K on a 6 story street side facade (rest of building is 7 stories/30 units. facade work ran us about $135K We had to do this twice in a 5 year period because of storm damage. Without a plan in hand, the variables that Contractors will tell you are huge, when you compare bids it is startling how the prices for similar items will vary, based on their own resources and way of doing the same job. Bid five+ in the hopes that you get back 3 usable bids. Insist that everything be line itemized, and that materials and labor be broken out separately and itemized. Retain the exclusive right to amend the RFQ so you can drop/add/modify sections or elements after receiving bids to make it affordable. We dropped out almost $40K in pre-cast custom sill replacements and substituted caulking all around and of any sill cracks thereby replacing only 5 of over 140+ sills. If you do not have a qualified building management construction person to Supervise the job from your end, then you will have to do it, overseeing the Architect. Do not allow your Management company to just supply you with a contractor, DO the work, interview architects and Engineers, interview Contractors with the Selected Architect/Engineer. This is a ferociously expensive project that can quickly go out of control, AND if not done correctly, can have you doing it over in less than five years at greater expense. A good architect and a good contractor will help you, will find ways to save you money and working together do it better, safer, and a hopefully more durable job. I would say we have been lucky, but we have good Management, and we made our own luck thru diligence.

I am sure I must have left somethings out, but this is the general idea, anyway.

As to windows and doors, and who is responsible. That will be in your proprietary lease, Bylaws etc. (I am Coop oriented), regardless of how it falls out, you do not want individual owners replacing windows with whatever they want, in whatever color they want, and whatever quality they feel like, You need to set up a building wide plan for replacements, pick you price point, color and style and stick firmly to it, and asses them all accordingly. You do want to hire an Architect to consult as it can be complicated as to choice and needs.

There is no viable shortcut around using experts. Whether it be Architects and Engineers, CPA's, Certiorari work or licensed tradesmen.

It will always save you either money, grief or both. These are big ticket projects, requiring permits and DOB filings. You don't want the supplier acting as his own supervisor, really! You don't need a big fancy architect or Engineering firm. You can do with a small practice office with really smart and skilled people. IT can be a solo outfit. Just do your homework, knock on doors, if you see a job being done, ask questions, find out if everyone is happy with the execution of the job. Drive around the neighborhood, Check habitat articles for Vendors who did well, and who to avoid, there are plenty of those around!
To do it right is a lot of work, to do it wrong is even more work,
Good luck.

Thank you for rating!

You have already rated this page, you can only rate it once!

Your rating has been changed, thanks for rating!

Introduce yourself to other members of Board Talk! Login below or register here.

Board Talk members who registered prior to March 9th, 2016 will need to reset their password.

Register

Forgot your password? Click here

> Join the conversation

Introduce yourself to other members of Board Talk! Log in below or register here.

Board Talk members who registered prior to March 9th, 2016 will need to reset their password.

Introduce yourself to other members of Board Talk! Login below or register here.
Board Talk members who registered prior to March 9th, 2016 will need to reset their password.

Ask the Experts

learn more

Learn all the basics of NYC co-op and condo management, with straight talk from heavy hitters in the field of co-op or condo apartments

Professionals in some of the key fields of co-op and condo board governance and building management answer common questions in their areas of expertise

Source Guide

see the guide

Looking for a vendor?